Good morning
Following our last related to the subject, please kindly note following info we could gathered and which is preliminary.
Please kindly note that the North berth is presently in a testing period and, despite some vessels have been loading at this berth, it isn't operating at its full capacity.
Please note following info:
NORTH BERTH
Owners: Renova S.A.
Location: Coronda River - Right Margin - Km 465,850 (Progresive of Km 465,850 of Paraná River)
4 berth defenses
4 Bollard of 100 Mt
Island pier with 2 mooring dolphins and 4 berthing dolphins, with 3 piles. Distance between piles axes: 55 mtrs
North dolphin: from center to center of pile 1: 62 mtrs
South dolphin: from center to center of pile 3: 62 mtrs
Distance between North dolphin and South dolphin: 275 mtrs
Max. LOA: 275 mtrs.
Air Draft at Datum (in meters): +28
Loading Arms: 3 Telescopic multidirectional arms w/Spoon Trimmers
Loading gangs: 2 (Grains/Byproducts)
Loading rate (Grain & Byproducts): abt 1 x 1500 Mt x hour (for the time being)
Loading rate (Oil): 1x8" Pipe (Oils) abt 800 Mt x hours (to be updated)
Draft alongside: no restrictions
Sailing draft: to be daily checked