· As per Terminal Operators (Obrinel SA) information, construction will be completed on October 2015.
· Location: inside Montevideo Port Area, Basin 2
· Said Terminal will have following facilities:
· Static storing capacity 123.000 Tons (12 silos) to be enlarged in additional 8 silos in a future stage.
· Pier 310 m long.
· Beam limitation up to post panamax size inclusive.
· No air draft limitation
· 1 conveyor belt – 3 loaders – no shifting required.
· A second conveyor belt would be installed in the future.
· Pier will be dredged to 13 m at zero tide.
· Port`s Main Access Channel is dredged to 11,5 m
· Presently undergoing deepening works up to 12,5 m at zero (sailing draft)
· In first instance hourly loading rate 1.200 Tons
· Average daily rate 20.000 tons approx.